Fredag 24 november 2006 02:12 skrev Adam Hardy:
(...)
>
> OK,
> here's a question that isn't obvious or a bug - to my mind at least :)
>
> I have 4 working days in my week. Three have working intervals with 2
> hours. The fourth has a working interval of 3 hours.
>
> Now when I enter the effort required on a task, I put in 5 hours, for
> example. Kplato then recalculates this into 2 days and 1 hour. I guess this
> is because I have set the Standard Worktime for a day to be 2 hours. Is
> that true?
>
> But that is only roughly correct, because really my average working day is
> 2.25 hours.
It uses the "Hour pr day" field (above) for this calculation.
>
> I would prefer to keep my task effort estimates as hours, instead of
> allowing kplato to recalculate them into days. Is there a way of doing
> this?
No, not atm. This widget has to be rewritten, though, due to problems with 
layout and navigation, so maybe in the future (koffice 2.0).
>
> Thanks
> Adam
> _______________________________________________
> kplato mailing list
> kplato at kde.org
> https://mail.kde.org/mailman/listinfo/kplato

-- 
Mvh
Dag Andersen