On Sunday 31 October 2004 11.22, Dag Andersen wrote:
> On Fredag 29 oktober 2004 20:35, Mark Tombs wrote:
> > Hi list
> >
> > I have a request for kplato functionality. Can it please, please,
> > please not auto-schedule the way MS Project does, or at least make
> > it optional? Its the most annoying thing. If I have an
>
> I think optional.
>
> > over-allocation or whatever, I prefer to be told about it and
> > decide myself what to do, rather than have my tasks shifting all
> > over the place.
>
> To be able to find out if there is conflicts the project needs to be
> scheduled, no?

Of course, but it doesn't need to be automatically scheduled for me. I am 
capable of entering my own task durations  (which doesn't have to be work * 
resources, like MSProject insists.) I want to be in control of my project 
plan, is all. I should be able to over-allocate resources if I want to :) An 
auto-schedule function should definitely exist, but in my opinion it should 
be something I request, then it happens, then my plan is left alone, if you 
understand what I mean.
>
> Hmm, maybe if we define a 'schedule only new task'-mode of calculation
> that effectively freezes existing tasks.
> So, if linked to existing tasks the new task will be scheduled in
> accordance with these but the old tasks will not be rescheduled.
> If there is enough float and resources it's ok, else conflicts are
> reported.
> What do say?
>
> > Don't know what the plans are re this, but thought I'd get in
> > early...
> >
> > thanks
> >
> > Mark
> > _______________________________________________
> > kplato mailing list
> > kplato at kde.org
> > https://mail.kde.org/mailman/listinfo/kplato