I've made a new task dialog (among other things) I would like you to
check out, especially Mark :)
I've added a scheduling type of 'FixedInterval' where you can define a
fixed start- and enddatetime for your task. If the time-part of both
datetimes are 0, the end date is interpreted as 'end of day' and
hence, duration = end - start + 1.
Default values for a task can be set in the config dialog.
(Expect to find some things not right, don't really have time to test
this now ;)