Systray jobs

Rob Scheepmaker r.scheepmaker at student.utwente.nl
Sat May 2 18:17:56 CEST 2009


On Saturday 02 May 2009 17:48:13 Sebastian Kügler wrote:
> On Friday 01 May 2009 18:40:00 Rob Scheepmaker wrote:
> > These are the main issues I encountered. Please try the systray from
> > trunk some time and give your feedback on these issues or provide your
> > own points.
>
> I've been seeing a logic issue for some time, I'll use this poke to finally
> tell you :-)
>
> When having multiple jobs running at the same time (say I'm copying two DVD
> images), the jobs popup shows the cumulated time of those. So if one job
> takes another 20 minutes, and the other one 15 minutes it'll show that
> these jobs will take 35 minutes, it should of course be 20 minutes (the
> maximum of those times).

D'oh, you're absolutely right, I'll fix it today.