[kplato] Duration less than a day? (was: request)

Dag Andersen danders at get2net.dk
Fri Nov 5 09:23:51 CET 2004


On Torsdag 04 november 2004 20:35, Mark Tombs wrote:
> On Thursday 04 November 2004 10.03, Dag Andersen wrote:
> > On Torsdag 04 november 2004 09:27, Mark Tombs wrote:
> > > On Thursday 04 November 2004 09.23, Dag Andersen wrote:
> > > > On Onsdag 03 november 2004 21:56, Claus Agerskov wrote:
> > > > > On Wed, 3 Nov 2004, Mark Tombs wrote:
> > > > > > Can the duration be less than a day? Claus wrote :
> > > > > >
> > > > > > "Duration is the calendar time of a task."
> > > > > >
> > > > > > If a task starts and finishes on the same day, it has a
> > > > > > duration of 1.
> > > >
> > > > How do you handle tasks with estimates that isn't multiple of
> > > > days? In general, how do you calculate a project like this?
> > >
> > > Thats where I think I and, it seems, the rest of the world have
> > > a different terminology ;) For me, Duration != work. The hours,
> >
> > Ok, I understand that, but eventually somebody is going to do the
> > work so I'm trying to figure out the connection.
> >
> > > estimate, work, whatever you call it, is seperate from the
> > > duration. A task can start and finish on the same day, have
> > > duration of 1, but an estimate of 1 minute, if you like. Now
> > > that I
> >
> > Hmm, so in this case the resource doing the work will have
> > 1day-1min free time, or a workload of 1min/1day?
> > You probably don't use tasklinks then, you define all
> > 'dependencies' by setting start- and/or endtimes?
> > What do you do if you have 2 tasks that depends on each other but
> > that can be done in 1 day?
> >
> > > write it like that, it doesn't seem to make much sense, but its
> > > how I've always worked. Maybe I should just be quiet now, as
> > > everyone else seems to disagree with me.
> >
> > No, no, if you are working that way, it must make sense, probably
> > others do the same somewhere.
> > We'll see if we can incorporate different ways of working without
> > making things impossible to understand.
> >
> > > > > Or?
> > > > >
> > > > > Duration is the time period from start timestamp to the end
> > > > > timestamp and can be measured in the time unit you want.
> > > >
> > > > That's how I see  it, too.
> > > >
> > > > > In some projects minutes can be crucial but in others
> > > > > months or - years even - are usable units for duration.
> > > > >
> > > > > Personal I would have the duration saved in seconds so I
> > > > > can choose the time unit I want when I will see the
> > > > > duration.
> > > >
> > > > It's saved in milliseconds, in a 64 bit int.
> > > >
> > > > > The most enjoyable greetings
> > >
> > > _______________________________________________
> > > kplato mailing list
> > > kplato at kde.org
> > > https://mail.kde.org/mailman/listinfo/kplato
>
> Maybe I should tell you what I have been using as a scheduler. I
> work for a partner to Niku, who produce enterprise portfolio
> management software. Their history is as a producer of project
> management software (or rather they bought ABT, who had a history
> as a producer of project management software). Some of you may know
> ABT Workbench, once called Project Manager Workbench (PMW). Its
> been around for donkeys years in various forms, and Niku have now
> open-sourced it (well, bits, anyway) so you can get it and try it
> yourself at www.openworkbench.org.
>
> It's Niku's flagship product, Clarity, that I want to integrate
> kplato with, as a replacement for workbench.
>
> Workbench doesn't allow you to set the start time of a task, and
> I've never heard anyone complaining yet ;) 
I'd say it depends on what you want the software to do for you.
> The resource knows how 
> many hours / minutes / seconds she is supposed to work on a task on
> which day. I still don't see how controlling the duration of a task
> to the minute helps you; 
I would have liked to see how a plan looked like, especially for cases 
like: 
Activity 1: You have a presentation to do at 2 o'clock for 2 hours.
Activity 2: You want, say, 7 hours to prepare.
How do you schedule these, and how do you show the dependency?
> in Workbench, the duration is simply the 
> number of days covered by the task, no more or less than that. Its
> the assigned work that matters, and the assigned work that you can
> control to the second.
How do you control it 'to the second' if you don't know when it's 
going to be finished? (except sometime during the day)
Hmm, maybe you mean the effort here?

Maybe I'm just slow, but well, as you probably can see, I'm still 
unsure, a bit confused and not quite certain of what benefits and 
restrictions this way of working gives :)
But I'm quite sure it should be possible to incorporate this work 
model also, I think it's more a question of finding a reasonable ui 
that covers it all.
>
> /Mark
>
>
>
> _______________________________________________
> kplato mailing list
> kplato at kde.org
> https://mail.kde.org/mailman/listinfo/kplato

-- 
Mvh,
Dag Andersen


More information about the kplato mailing list