On Wednesday 03 November 2004 22.34, Claus Agerskov wrote:
> On Wed, 3 Nov 2004, Mark Tombs wrote:
> > On Wednesday 03 November 2004 09.29, Dag Andersen wrote:
> > > > Task code: I gather you want to enter a code manually, but should
> > > > it be number only or text, and should a 'default' be generated?
> >
> > The only reason I put a task code there is because a system I hope to
> > integrate kplato with has a task code, which is text and uniquely
> > identifies the task in the project.
>
> Are you talking about a Work Breakdown Structure Codes (WBS Codes)?
>
> There should absolutely be WBS Codes where the user can use multiple ways
> to number them like:
>
> First level: 1 A VI 1
> Second level: 1.A A-001 VI ix 1.01
> Third level: 1.A.01 A-001-a VI ix a 1.01rc1
>
> As the last example show it should be possible to create customized
> numbering lists like a1,a2,b1,b2,b3,rc1,rc2,final.
>
> But there should also be a field for a specific task code which doesn't
> change when the structure changes.
thats the one I mean.
>
> The most enjoyable greetings