Thomas Zander wrote:
> so two groups of radiobuttons:
>
> Project scheduling: (won't effect start/end time)
> o ASAP
> o ALAP
> Project start/end
> o Start not earier then
> o Finish not later then
> o Must start on
>
> Right?
These look sensible. ASAP and ALAP don't affect pert/cpm because they
are essentially resource allocation problems. ASAP make sense if you
want to avoid the risk of overrunning on non-critical activities. ALAP
makes sense if the resources are expensive and hired/rented at the point
of need (e.g. hiring a large crane for construction) because that delays
capital expenditure.
I guess project start/end time is to allow the possibility that the
project itself may have some slack. It certainly makes sense to build
that in.
--
JDL