[Digikam-devel] digiKam 0.9.1 string freeze - release plan

Marcel Wiesweg marcel.wiesweg at gmx.de
Sun Feb 25 14:11:27 GMT 2007


> > String freeze: today (2007-02-11)
> > 0.9.1-beta1 : 2007-11-02.
> > 0.9.1-RC : 2007-18-02.
> > 0.9.1-final : 2007-25-02.
> >
> > So I would like to ask you that translations are available for the final
> > release in two weeks. Of course any previous commit will be welcome, as
> > we are going through intensive testing.
>
> Can you put off the release for a few days?
> As far as I can see, there have been a few changes in digikam docbook,
> and they have not been yet propagated to .pot files nor .po files, so we
> cannot translate them. Without that I cannot even generate documentation
> (translation must be complete for docbook generation).

The release has already been delayed by one week. RC2 today, final release 
next weekend.

>
> 	Krzysztof Lichota (Polish team)



More information about the Digikam-devel mailing list