2.8.x maintenance plan and 2.9 ?

Cyrille Berger cberger at cberger.net
Wed Apr 9 09:06:56 BST 2014


On 2014-04-04 09:55, Boudewijn Rempt wrote:
>> So what about 2.9 ? I could suggest branching early august and a 
>> release
>> in September/October ? Or do you want a release earlier/later ?
>> 
> 
> It's hard to say about 2.9 :-). I expect there will be some delays
> with that release as it's the last before we port (again) to Qt5, but
> I think it's a good plan to aim for a september release. With a bit of
> luck and effort we could still make February 2015 for the 3.0 release
> then -- if we restrict ourselves to porting and not to refactoring.

Well we could have a June/Jully 2.9 release and an around November 2.10 
release. That would satisfy Jaroslaw and gives less reason to delay the 
september release. But I guess it also depends how much new features are 
coming.

-- 
Cyrille Berger Skott