2.6 Release Schedule

Cyrille Berger Skott cberger at cberger.net
Sat Aug 18 07:08:26 BST 2012


On Tuesday 07 Aug 2012, Boudewijn Rempt wrote:
> On Tuesday 07 August 2012 Aug, Cyrille Berger Skott wrote:
> > Hi,
> > 
> > Here is the suggested schedule for 2.6:
> > 
> > September 7th alpha tagging
> > September 28th branch+beta tagging
> > October 19th RC tagging
> > 
> > Release expected early November
> 
> Right now, I'm having a bit of a difficulty planning because I need to get
> Krita Sketch done by October as well. And there's the lut docker, which I
> can only finish properly when lcms2 gets its next release, and then
> there's the new opengl canvas... I don't say we won't be able to make
> this, but I just want to register an advance warning that for Krita at
> least, a purely time-based release is going to be difficult this time.
Anyone else has an opinion on that ?

As far as I am concerned, if the lut docker is not in 2.6, there is still 2.7 
around the corner. Or are you thinking that with an extra month you will have 
time to finish all that ?

-- 
Cyrille Berger Skott



More information about the calligra-devel mailing list