[RkWard-devel] 0.4.6 release timeline
SJR
stefan_roediger at gmx.de
Wed Jan 31 20:55:26 UTC 2007
Am Mittwoch, 31. Januar 2007 19:58 schrieb Thomas Friedrichsmeier:
> Hi,
>
> since the 0.4.5 release, we've seen a whole bunch of new and improved
> plugins coming in, but also some useful additions in the core application.
> Time to start thinking about the next release.
>
> I'd like to propose the following timeline:
>
> Today until 2007-02-07 (next Wednesday): Feature completion phase:
> During this time, addition of new features is still possible. However,
> please do not start anything new, unless you are reasonably sure, you can
> complete it until the given deadline. If you have trouble completing a
> feature/plugin you have already started by the deadline, please ask for
> help.
> If you have nothing new to do, consider helping with documentation, testing
> plugins, or similar tasks (there's plenty to do).
> @Roland: Did you get any further with the "Run Block" functionality, and or
> the icons? Do you think you can get this done by next Wednesday?
>
> Sunday 2007-02-04: 0.4.6pre1 Release, start of testing phase:
> First preview release, call for testing. Translators may start translating,
> but there could still be some minor string changes (see below). Depending
> on how much time you will have available after 2007-02-11, you may want to
> hold off on the translation.
>
> Wednesday 2007-02-07: Feature freeze for 0.4.6.
> The 0.4.6 release branch will be created, and no new features will enter
> the release. New features may be added to the SVN trunk, but those will not
> become part of the 0.4.6 release. Documentation additions and bugfixes will
> be merged into the release branch.
>
> Sunday 2007-02-11: 0.4.6pre2 Release, string freeze:
> Second preview release, second call for testing. Hopefully most bugs will
> be fixed by now, but time for another close look, especially at the
> features that were added until 2007-02-07.
> No string changes are allowed from now on, unless they fix critical bugs
> (since documentation still isn't translatable, documentation changes are
> still possible). Hence, this is a good time to start translations, if you
> have not already done so already (see above).
>
> Wednesday 2007-02-14: Deadline for translations
>
> Thursday 2007-02-15: Targeted release date.
>
> Does this seem alright to you? If not, please speak up now. It's not too
> late to change everything, yet.
>
> Regards
> Thomas
Wow. This means less than a month after the 0.4.5 release.
Though I have very limited time right now I consent and try to do my best.
Translation possible for sure. New plugins with some tweaking or a little help
too (they are not to complicated). Documentation is hard to say. There are
many that need some help information.
@Prasenjit Kapat. Will you take care of that for the distribution plugins?
Basically we can add the same information to each of the plugins and rather
link the user to the R-help pages. What do you think?
Regards
Stefan