KDE SC 4.11 Release Schedule (bis)
Albert Astals Cid
aacid at kde.org
Mon Mar 4 23:43:53 UTC 2013
A few months ago we were discussing changes regarding 4.11
http://mail.kde.org/pipermail/release-team/2013-January/006708.html
The changes I suggested where
***************
1) Drop Betas to 1
It doesn't seem "to me" that having extra betas gives us much more quality,
so my suggestion is to drop Beta 2 and move Beta 1 to happen in Beta 2 time
(moving also Hard Freeze) which gives us 2 more weeks for feature
development
2) Drop RCs to 1
Same thing, it did not feel to me as that it gave us much, drop RC2 and RC1
one week into the future
3) Increase RC time between tag and packaging
One day between tagging and release is crazy, let's have 5/6 days as we
have for the other releases
4) Don't release if any if the tests are failing in builds.kde.org
If we have tests, they have to work
5) Introduce an pre-commit check after Feature freeze
That check would look for "SCHEDULE-CHECK: bugfix" in the commit log and
reject the commit otherwise. This would fix the fact that people seem to be
commiting features and then saying "oh, but i did not read the emails you
send every month saying we are in a feature freeze so i did not know I
couldn't do this", this way at least they would be forced to say their
stuff is a bugfix.
***************
I have gone through all of the mails of the thread and if i did not do a
mistake in the interpretations of the emails, these are the "results"
1) Drop Betas to 1
2) Drop RCs to 1
Albert Astals Cid - yes
Christian Mollekopf - yes
Sebastian Kügler - yes with comments
Martin Gräßlin - No
3) Increase RC time between tag and packaging
Albert Astals Cid - yes -> Reword schedule
Sebastian Kügler - Reword schedule
Torgny Nyblom - Reword schedule
4) Don't release if any if the tests are failing in builds.kde.org
Albert Astals Cid - yes
Michael Palimaka - yes
Christian Mollekopf - yes
Martin Gräßlin - yes with comments
5) Introduce an pre-commit check after Feature freeze
Torgny Nyblom - yes
Christian Mollekopf - yes with comments
Albert Astals Cid - unsure
So my reading is that we should do 3 as a reword of the schedule and 4 for
sure.
I'm a bit unsure about 1, 2 and 5. Anyone has extra opinions to share? I'd
like to have a finalized schedule for 4.11 next week.
Cheers,
Albert