Proposed schedule for 4.12
Albert Astals Cid
aacid at kde.org
Tue Aug 20 18:44:37 UTC 2013
El Dissabte, 3 d'agost de 2013, a les 20:19:48, Albert Astals Cid va escriure:
> Please let's try to keep this discussion in release-team, I'm just CC'ing
> k-c- d because Alex's discussion about changing the release happened there.
>
> At the Release Team BoF at Akademy I was tasked to come up with a proposed
> schedule for 4.12 with simplified freezes, since it was agreed so many
> freezes confused our contributors.
>
> Here's my attempt
> http://techbase.kde.org/Schedules/KDE4/4.12_Release_Schedule
>
> Basically the schedule looks like
>
> 30 October (everything except documentation is frozen)
> +1 week Beta 1 Tag+Release: November 6
> +1 week Beta 2 Tag+Release: November 13
> +1 week Beta 3 Tag+Release (with documentation freeze): November 20
> +1 week RC Tag+Release: November 27
> +2 week Final Tag: December 11
> +1 week Final Release: December 18
>
> Summary:
> * There's just one freeze
> This should make it easier to everyone know when to commit something or
> not. Exception for documentation that you get 3 weeks more, rationale is
> that documentation team works after features are finished so we give them
> some more time for the last-minute finished features
>
> * We do Betas/RC more often
> Every week instead of every 2 weeks, this way we achieve (if distros
> deliver) more "interactivity" with bugrepors+fixes since people is always
> testing something that is closer to the tip of the code (it happens fairly
> usually that someone reports a bug and it was fixed "last week" already,
> wasting "user testing" and "bug answering" resources)
>
> Comments?
Since noone complained, i've used the magic wand and made it official.
Cheers,
Albert
>
> Cheers,
> Albert
> _______________________________________________
> release-team mailing list
> release-team at kde.org
> https://mail.kde.org/mailman/listinfo/release-team