Lørdag 29 september 2007 12:57 skrev Felix Salfner:
> Hi,
>
> is there any way to remove links between tasks in the WBS?
Yes, doubleclick the task link (in the gantt view) and you'll get a dialog.
>
> Thanks in advance
> Felix
>
> _______________________________________________
> kplato mailing list
> kplato at kde.org
> https://mail.kde.org/mailman/listinfo/kplato
--
Mvh
Dag Andersen