We want to display three curves to answer this need :
" The best charting available is
to display Budgeted Cost of Work Scheduled vs. Budgeted Cost of Work
Performed (Schedule Variance); and Budgeted Cost of Work Performed vs.
Actual Cost of Work Performed (Cost Variance)."
On the X-coordinate : the current duration of the project
On the Y-coordinate : the percentage of the budgeted cost of work
Scheduled...etc
It will be integer points that we need to join with graphical curves.
A simple chart with some colours ;)
2007/1/18, Thomas Zander <zander at kde.org>:
> On Wednesday 17 January 2007 15:27, Frédéric Lambert wrote:
> > We are working on the possibility to display 3 curves like mentionned in
> > previous post.
>
> There still is some confusion around this issue, and that stems mostly from
> the question if kchart is the right solution.
>
> Could you explain what you need this for?
> What kind of data (examples please) do you want to display on screen?
>
> Thanks!
> --
> Thomas Zander
>
>