[kplato] Summary of Data Discussion
Jim Sabatke
kplato@kde.org
Thu, 21 Jun 2001 13:52:15 -0500
One of my pet peeves about M$ Project is that a LOT of values get
changed when you enter data. It is maddening.
bilbo wrote:
><snip>
>
>I was talking to a friend about this last night and one of his pet
>hates with MS Project is that if he changes the duration of a task it
>changes the effort as well, he'd like to be able to hold one of these
>invariant whilst changing the other on a task by task basis.
>Presumably a report to highlight the under-allocation of resource
>where the duration is reduced but the effort remains the same
>would be standard? (I don't see over-allocation being as big a
>problem but ....)
>
Man days is another kind of risk. There is inefficiency built in when
splitting a job into parts for different resources. My favorite
expression is (From "The Mythical Man Month") "You can't get 9 women to
deliver a baby on 1 month."
>
>In sw projects I'm used to quoting estimates for tasks as, for
>example, 30 mandays +/- 5days. Does this translate easily into
>risk or is risk to be handled separately, and if so should we be
>including uncertainty? It could be required to enter the base
>estimate plus the positive uncertainty (35 days from above) but this
>smacks of imposing an approach and reducing flexibility.
>Is it only (some) software projects that work this way - surely other
>disciplines have similar problems with estimation?
>
>regards,
> Bill
>_______________________________________________
>kplato mailing list
>kplato@master.kde.org
>http://master.kde.org/mailman/listinfo/kplato
>
>
--
Jim Sabatke
SuSE 7.1 Linux
Kernel - 2.4.0
http://www.execpc.com/~jsabatke
"People tell me that I'm fading fast, that I can't last the whole night through" Janis Ian