wreissenberger added a comment.
  Hm, quite complicated. Has this ever worked? Nevertheless, I think when running multi-day-schedules, I would use "Remember job progress". In that case I think this situation would not happen.
  
  What is quite good visible from your example, that setting jobs to completed when they hit a constraint is not a good idea. Complete means that the defined amount of frames have been taken - nothing else.
  
  Therefore I would like to proceed in that direction.
  
  Meanwhile, it would be great if we find a way to simulate the regression above in a reasonable timeframe. I tried it but did not succeed. It is not sufficient sending the scheduler asleep. Maybe the scheduler needs to pass a time where no job is executable due to constraints and constraints become valid again.
REPOSITORY
  R321 KStars
REVISION DETAIL
  https://phabricator.kde.org/D22446
To: wreissenberger, mutlaqja, TallFurryMan
Cc: kde-edu, narvaez, apol
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://mail.kde.org/pipermail/kde-edu/attachments/20190920/e720fbb5/attachment.html>
    
    
More information about the kde-edu
mailing list