Final release schedule 4.3.0 + soft freeze

Tom Albers tomalbers at kde.nl
Sat Apr 11 22:55:14 BST 2009


Hi,

After months of feature development, it is time to prepare for the 4.3.0 release. The release team has put up the release schedule on: http://techbase.kde.org/Schedules/KDE4/4.3_Release_Schedule so we can release at July 28th, exactly 1 year after 4.1 and 6 months after 4.2.

The schedule has been setup so that the first release candidate is released just before akademy, which is the time that branching happens. So, at akademy everyone can either hack on new features or test and fix last minute bugs in preparation of the release.

The first deadline is next Thursday. By then the soft freeze hits. Trunk is from that day on frozen for feature commits that are not listed in the  planned feature document at http://techbase.kde.org/Schedules/KDE4/4.3_Feature_Plan . Only bugfixes and the code implementing the listed features are to be committed. The feature list also closes that day. Features not already finished or listed on the planned features page will have to wait until KDE 4.4. 

Best,

Toma
Release Team


More information about the kde-core-devel mailing list