So we have:
== 2.9.3 ==
* Tagging April 25th
* Release April 29th -- Cancelled (even if it can be available for
download in some distros)
Now how about:
== 2.9.4 ==
* Tagging May 2nd
* Release May 6th -- so in one week after 2.9.3 as we suggested
== 2.9.5 ==
* Tagging May 30th
* Release June 3rd -- pushed by on week because of the above
2.9.6+ -- depending on interest/needs/resources, see my next email
--
regards, Jaroslaw Staniek