2.4 release schedule
C. Boemann
cbo at boemann.dk
Mon Jul 11 17:30:40 BST 2011
On Monday 11 July 2011 18:08:58 Cyrille Berger Skott wrote:
> Hi,
>
> There was a discussion on IRC about it a little while ago about the release
> schedule, one of the conclusion was that soft-freeze was not needed
> anymore.
>
> But some people thought that the freezing time would be too long, so here
> is an alternative schedule.
>
> August 31th -> soft freeze, no more features in master, features in
> master are restricted to features discussed
> before hand and that can justify an
> September 7th -> beta1 is tagged
> September 14th -> beta1 is released
> September 30th -> beta2 is tagged
> October 5th -> beta2 is released
> October 12th -> String freeze, any changes to a string in futurestable
> needs to be discussed with the translation
> teams (except for typo that are bug fix and
> you only need to ping the translation teams) It also means no new features
> can be added October 21th -> beta3 is tagged
> October 26th -> beta3 is released, master is branched into
> "futurestable", and master get open again
> for new features, and "futurestable" is the branch were bug fixes for 2.4
> need to go
> November 18th -> RC1 is tagged, "futurestable" is closed, and merged in
> "stable"
> November 23th -> RC1 is released
>
>
> It is worthwhile to remember that while new features are allowed in the
> beta cycle, it should be the exception, not the norm.
>
> So what do you think ? Is it better with the feature exception, or do most
> people prefers no feature exception ?
Looks good to me
More information about the calligra-devel
mailing list