2.4 Release Plan
Boudewijn Rempt
boud at valdyas.org
Wed Jan 12 19:32:04 GMT 2011
On Wednesday 12 January 2011, C. Boemann wrote:
> On Wednesday 12 January 2011 20:09:59 Boudewijn Rempt wrote:
> > On Wednesday 12 January 2011, Cyrille Berger Skott wrote:
> > > Hi,
> > >
> > > Time to work on a release schedule for the first calligra release, aka
> > > 2.4 (and not 1.0 :) ).
> > >
> > > If we were to strictly follow our schedule, we would have schedule that
> > > looks like this: (with year+1, ie 2010->2011)
> > >
> > > http://community.kde.org/Calligra/Schedules/KOffice/2.2/Release_Plan
> > >
> > > Meaning we should have a soft-freeze tomorrow... :) Since KOffice 2.3
> > > took much more time to be ready, I would be tempted to suggest to push a
> > > little bit the release of the RC1 to the end of May (giving us one more
> > > month).
> > >
> > > So the real question is what do you guys prefers ? a RC1 at the end of
> > > april (actually right on my birthday ;P) or a RC1 at the end of May ?
> >
> > With all the time the creation of calligra has eaten away from hacking
> > time, I support another month as well. I'd even support two months, if
> > that helps us make a real bang with the first calligra release.
> Yeah, but I'm torn because we should also remember that the longe we go
> without releasing anything the longer it takes for us to establish ourselves
>
> Right now we are nothing, to the outside world.
We could go with a really long and relaxed beta period :-)
--
Boudewijn Rempt | http://www.valdyas.org, http://www.krita.org
More information about the calligra-devel