2.4 Release Plan

Boudewijn Rempt boud at valdyas.org
Wed Jan 12 19:09:59 GMT 2011


On Wednesday 12 January 2011, Cyrille Berger Skott wrote:
> Hi,
> 
> Time to work on a release schedule for the first calligra release, aka 2.4 
> (and not 1.0 :) ).
> 
> If we were to strictly follow our schedule, we would have schedule that looks 
> like this: (with year+1, ie 2010->2011)
> 
> http://community.kde.org/Calligra/Schedules/KOffice/2.2/Release_Plan
> 
> Meaning we should have a soft-freeze tomorrow... :) Since KOffice 2.3 took 
> much more time to be ready, I would be tempted to suggest to push a little bit 
> the release of the RC1 to the end of May (giving us one more month).
> 
> So the real question is what do you guys prefers ? a RC1 at the end of april 
> (actually right on my birthday ;P) or a RC1 at the end of May ?
> 
> 

With all the time the creation of calligra has eaten away from hacking time, I support another month as well. I'd even support two months, if that helps us make a real bang with the first calligra release.

-- 
Boudewijn Rempt | http://www.valdyas.org, http://www.krita.org