Hi,
Time to work on a release schedule for the first calligra release, aka 2.4
(and not 1.0 :) ).
If we were to strictly follow our schedule, we would have schedule that looks
like this: (with year+1, ie 2010->2011)
http://community.kde.org/Calligra/Schedules/KOffice/2.2/Release_Plan
Meaning we should have a soft-freeze tomorrow... :) Since KOffice 2.3 took
much more time to be ready, I would be tempted to suggest to push a little bit
the release of the RC1 to the end of May (giving us one more month).
So the real question is what do you guys prefers ? a RC1 at the end of april
(actually right on my birthday ;P) or a RC1 at the end of May ?
--