> > * Let's make a monthly calligra snapshot that's advertised as reasonably
> > stable and full of you-need-to-try-this goodness until we are at a point
> > where we can start a real release schedule
> >
> >
> >
> > * first release: march 1st, from then on every 1st of the month
> >
> >
> >
> > * internal numbering starts at 2.3.80
> >
> >
> >
> > * external we call it the "march snapshot", "april snapshot"
>
> i support that
I will just shift the march release from one week. to march 8th.
--