Release plan for 2.6
Matěj Laitl
matej at laitl.cz
Sun Apr 29 12:45:44 UTC 2012
On 29. 4. 2012 Myriam Schweingruber wrote:
> since we need to decide on a release plan for 2.6 let me make a suggestion:
>
> To give Matej some more time for his tests we could release a 2.6 beta
> on June 4th, then do the release 2 weeks later, on June 18th. What do
> you all think?
The iPod collection merge went rather smooth AFAIK, so I'll probably need less
time. Something like beta on May 21st or a few days earlier would work fine
with me. (GSoC students could then base their work on 2.6-beta)
Are 2 weeks enough for translators, testers & packagers to catch up? I
personally would give them a week or two more, but I have little experience
with releasing Amarok.
Cheers,
Matěj
More information about the Amarok-devel
mailing list