Hi,
I have updated the release plan for maintenance release for 2.8:
http://community.kde.org/Calligra/Schedules/2.8/Release_Plan
2.8.3 and 2.8.4 might be readjusted depending on the rate of bug fixing,
and further releases might be added with the same consideration.
So what about 2.9 ? I could suggest branching early august and a release
in September/October ? Or do you want a release earlier/later ?
--
Cyrille Berger Skott
More information about the calligra-devel